The project adopts 222 pieces 260 polysilicon solar modules, 2 sets of INVT BG30KTR inverter. Project adopts the stent tiling model, the total installed capacity is 57.72KWp, 380v low voltage grid-connection. The annual power generation is expected to be 45,800 degrees.
The project adopts the cooperation mode of contract energy management, building owners provide roof for free and solar power generation is sold to buildings owners at current electricity prices by 80% discount.
energy saving benefits table of 57KW distributed solar project investment in Jiangbei District Chongqing Province
NO. | Program | Value |
1 | Total Project Investment | 490.3 thousand |
2 | IRR ( total investment ) rate of return | 2.94% |
3 | First year power generation | 44.7 thousand |
4 | Static investment payback period (after tax) | 14.61 years |
5 | Total investment rate of return | 2.68% |
6 | Comprehensive price (tax included) 1 - 20 years | 1.06 yuan/KWh |
Comprehensive price (tax included) 20-25 years | 0.64 yuan/KWh | |
7 | annual savings of standard coal | 16.50 tons |
8 | annual reduced SO2 emissions | 1.23 tons |
9 | annual reduced CO2 emissions | 40.72 tons |
4.8 m building parapet height is the project difficulty, we need to build 4.3m and 0.3m cement foundation to ensure that the solar module is not covered by the parapet.
The project achieves grid-connection in January 2017 and is in normal operation at present.
parapet project site photo
Distributed solar project site photo
Nuestro sitio utiliza cookies para brindarle una mejor experiencia en el sitio. Al continuar navegando por el sitio, acepta nuestro uso de cookies de acuerdo con nuestra Política de cookies.