Soutien

Soutien

Bibliothèque FAQs
Q
How to adjust GD20-EU's carrier frequency in the parameters?
2020-10-28
A

The carrier frequency is an important parameter for the VFD operation. If increase it, the output waveform will be better and the electromagnetic noise will be smaller, but it will increase the inverter's operating temperature, poor heat dissipation, and greater leakage current. The factory default parameters have been reasonably set, and adjustments are not recommended. If it is adjusted larger, the inverter needs to be derated for use. For every additional 1k, derate by 10%.

Q
Why use GD20UL to drive the motor, consumes more electricity instead of saving energy?
2020-10-28
A

The inverter itself needs to consume a part of energy. The inverter has a soft start function, which can reduce the starting impulse current of the motor; the frequency can be adjusted to realize the motor speed regulation. When using a inverter, the motor has been working at the rated frequency. In this case, energy saving cannot be achieved. When the water pump or fan is driven by frequency conversion, it can replace the valve to adjust the flow, which can save energy.

Q
How does GD20UL use multi-step speed function?
2020-10-22
A

For example, the parameters are set as follows:
P00.01 1 Terminal control
P00.06 6 Multi-speed setting
P01.18 1
P01.21 1
P05.00 1 HDI selection
P05.01 16 S1
P05.02 17 S2
P05.03 18 S3
P05.04 19 S4
P05.09 1 HDI speed terminal
P10.04 40% S1 on, 20Hz
P10.08 60% S1+S2 on, 30Hz
P10.16 80% S1+S2+S3 on, 40Hz
P10.32 100% S1+S2+S3+S4 on,50Hz

Q
How many kWh can 100AH battary storage?
2020-10-22
A

Generally, the battary voltage is around 14~10V discharging from full to emty. So 100AH*(14+10)/2V=1200VAH=1.2kWH

Q
What's the maximum input voltage fluctuation range for GD5000?
2020-10-22
A

When the input voltage fluctuates by -15% to 10%, the MVD can run at full load, and when the input voltage fluctuates by -35% to +20%, the MVD must run at reduced amount.

Q
Which series of small PLC can support Ethernet in your company?
2020-10-22
A

IVC2, IVC3 series.

Q
For GD100-PV, how to configure the photovoltaic panel between Voc and Vmp?
2020-10-22
A

Voc is the open circuit voltage of the photovoltaic panel, and Vmp is the maximum power point voltage. When calculating, use Vmp to calculate the number of photovoltaic panels. After calculation, you need to consider that the total Voc voltage is less than the overvoltage point of GD100-PV.In the manual, there are the suitable solar panel conficuration.

Q
How to control the inverter via mobile phone Bluetooth?
2020-10-15
A

GD350 needs to be equipped with a Bluetooth card, scan the QR code on the inverter, download and install INVT Workshop, and open the mobile phone Bluetooth to connect to the inverter. See the video link below for more steps.

https://www.youtube.com/watch?v=zkC-eGiBJ8I

Q
How to control theGD350 through Wifi?
2020-10-15
A

GD350 needs to be equipped with a Wifi card, scan the QR code on the inverter, download and install INVT Workshop, and open the mobile phone Wifi to connect to the inverter hotspot. See the video link below for more steps.

1112131415 Show:
Vous pouvez également voir:
Présentation du serviceService à valeur ajoutéeFormation TéléchargerQFPsRequête de produit
Demande de produit
Nom:*
Société:
Pays:*
Adresse e-mail:*
Téléphone:
Teneur:*

Notre site utilise des cookies pour vous offrir une meilleure expérience sur site. En poursuivant votre navigation, vous acceptez notre utilisation des cookies conformément à nos Politique relative aux cookies.